Edgewood Hall Renovation & Expansion
HARFORD COMMUNITY COLLEGE Project Number: C144106 Council District: E Location: Churchville Est. Debt Service:
Operating Budget Impact
Revenues:
Expenditures: Cost Savings: None:
$86,614 (annual)
X
Expended/Encumbered as of 2/9/22: $3,464,575
Project Schedule/Status: This project will be closed and removed from the Capital Improvement Program following completion of the audit in July, 2022.
PROJECT DESCRIPTION: This project has been moved up on the Facilities Master Plan due to systemic problems. The project will consist of a major renovation to solve these problems and add two small additions to meet programmatic needs resulting in a building that will serve the College's needs for the next 25 years. The two most critical systemic issues are the roofing and the HVAC systems. The seamed metal roof is rusting where it meets the concealed drain. A major leak caused collapsing ceiling tiles during severe weather. The two pipe HVAC system needs to be replaced with a four pipe system and wall units replaced with VAV boxes. During renovation sinks will be added in critical classrooms, flooring, paint, ceiling tiles, and bathroom fixtures will be replaced. Expansion will add two new multipurpose labs, a computer classroom, a small office addition, and a telecom closet.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
632,000
632,000
632,000
0
0
Construction
7,692,575
7,692,575
7,692,575
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
8,324,575
0 8,324,575
0
0
0
0
0
8,324,575
FUNDING SCHEDULE
R7100 Prior Bonds R7920 State Bonds
3,464,575 4,860,000
3,464,575 4,860,000
3,464,575 4,860,000
0 0 0
0 0 0
Total Cost:
8,324,575
0 8,324,575
0
0
0
0
0
8,324,575