FY 23 APPROVED CAPITAL BUDGET
Bel Air Library Renovations
LIBRARIES Project Number: Council District:
Operating Budget Impact
L234120
C
Revenues:
Location:
Bel Air
Expenditures: Cost Savings: None:
Est. Debt Service:
$20,000 (annual)
X
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status: FY 22: Design FY 23: Construction
PROJECT DESCRIPTION: This project will provide funding for the comprehensive renovation to the Bel Air Library to include site, roof, exterior, interior, mechanical, plumbing, electrical, fire/life safety and conveyance system.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
800,000
800,000
800,000
0
0
Construction
1,400,000 1,400,000 17,500,000
18,900,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
0 2,200,000 2,200,000 17,500,000
0
0
0
0 19,700,000
FUNDING SCHEDULE
R7000 Future Bonds R3399 State Other
800,000
800,000 16,000,000
16,800,000 2,900,000
1,400,000 1,400,000 1,500,000
0 0 0
0 0 0
Total Cost:
0 2,200,000 2,200,000 17,500,000
0
0
0
0 19,700,000
152