FY 23 APPROVED CAPITAL BUDGET
Waste-To-Energy Facility Closure
SOLID WASTE Project Number: Council District:
Operating Budget Impact Revenues:
D145602
A
Location:
Joppa
Expenditures: Cost Savings: None:
Est. Debt Service:
(annual)
Expended/Encumbered as of 2/9/22: $3,140,496
Project Schedule/Status:
PROJECT DESCRIPTION: This project provides for decommissioning, demolition and site restoration for the Harford Waste-To-Energy facility. FY 23 Paygo funding is Special Dedicated Paygo.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
400,000
400,000
400,000
0
0
Construction
7,763,753 5,000,000 12,763,753
12,763,753
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
8,163,753 5,000,000 13,163,753
0
0
0
0
0 13,163,753
FUNDING SCHEDULE
R8750 Paygo
8,163,753 5,000,000 13,163,753
13,163,753
0 0 0 0
0 0 0 0
Total Cost:
8,163,753 5,000,000 13,163,753
0
0
0
0
0 13,163,753
190