FY 23 APPROVED CAPITAL BUDGET
Bridge and Road Scour Repairs
HIGHWAYS - BRIDGES Project Number:
Operating Budget Impact
H064501 Multiple Various
Council District:
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
x
Expended/Encumbered as of 2/9/22: $1,721,258
Project Schedule/Status: FY 22: Rock Station Road Various projects are continuously being designed and constructed under this account.
PROJECT DESCRIPTION: Most of the bridges in the County cross over streams and there are many roads that were built adjacent to streams as well as crossing over streams. All of these are vulnerable to the cumulative damage from small storms and the severe damage from major storms. The damage includes the undermining of bridge abutments and piers and the removal of the roadbed material from the stream/road banks. Severe damage can lead to bridge failure or road closure. These funds will be used to design and install scour countermeasures to rebuild or repair damaged areas or to protect areas that are vulnerable to future stream scour.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
175,000
30,000
205,000
30,000
30,000
30,000
30,000
30,000
355,000
5,000
5,000
5,000
Construction
1,880,000 200,000 2,080,000 200,000 200,000 200,000 200,000 200,000
3,080,000
Inspection Fees
165,000
20,000
185,000
20,000
20,000
20,000
20,000
20,000
285,000
Equipment/Furnishing
0
0
Total Cost:
2,225,000 250,000 2,475,000 250,000 250,000 250,000 250,000 250,000
3,725,000
FUNDING SCHEDULE
R8750 Paygo
2,225,000 250,000 2,475,000 250,000 250,000 250,000 250,000 250,000
3,725,000
0 0 0 0
0 0 0 0
Total Cost:
2,225,000 250,000 2,475,000 250,000 250,000 250,000 250,000 250,000
3,725,000