FY 23 APPROVED CAPITAL BUDGET
Boggs Road Bridge #66
HIGHWAYS - BRIDGES Project Number:
Operating Budget Impact
H214501
Council District:
B
Revenues:
Location:
Fallston
Expenditures: Cost Savings: None:
Est. Debt Service:
$10,000 (annual)
x
Expended/Encumbered as of 2/9/22: $255,651
Project Schedule/Status: FY 21: Design is 30% complete. FY 22-23: Design/right of way/permits FY 24: Construction
PROJECT DESCRIPTION: The purpose of this project is to replace the bridge that carries Boggs Road over Long Branch. The existing bridge is a single lane steel beam, concrete deck structure with bituminous concrete surfacing that is posted for 13 tons. The two lane approach on both ends of the single lane bridge are in horizontal curves that restrict sight distance across the bridge. The existing area is developing rapidly and is not able to carry the expected heavier traffic volumes. It is not possible to place a two lane deck on the existing narrow abutments. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
280,000 100,000
380,000 20,000
380,000 20,000
20,000
Construction
0 1,400,000 0 150,000
1,400,000
Inspection Fees
150,000
Equipment/Furnishing
0
0
Total Cost:
300,000 100,000
400,000 1,550,000
0
0
0
0
1,950,000
FUNDING SCHEDULE
R7000 Future Bonds R7100 Prior Bonds
100,000
100,000 1,550,000
1,650,000
300,000
300,000
300,000
0 0 0
0 0 0
Total Cost:
300,000 100,000
400,000 1,550,000
0
0
0
0
1,950,000
282
Made with FlippingBook Online newsletter creator