FY 23 APPROVED CAPITAL BUDGET

Glenville Road Bridge #30

HIGHWAYS - BRIDGES Project Number:

Operating Budget Impact

H164501 Multiple

Council District:

Revenues:

Location:

Churchville

Expenditures: Cost Savings: None:

Est. Debt Service:

$3,250

(annual)

X

Expended/Encumbered as of 2/9/22: $159,660

Project Schedule/Status: FY 22-23: Design and right of way FY 25: Utility relocation and construction

PROJECT DESCRIPTION: This project is to replace the bridge that carries Glenville Road over Mill Brook. The existing bridge is a single lane, steel beam, concrete deck structure. The existing concrete deck, exterior beams, and wingwalls are severely deteriorated and there is evidence of scour under the western abutment. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.

EXPENDITURE SCHEDULE

Approp Total

Cost Element

Prior

FY 2023

FY 2024 FY 2025 FY 2026 FY 2027 FY 2028

TOTAL

Engineering/Design Land Acquisition

460,000 350,000

810,000 50,000

810,000 50,000

50,000

Construction

0 0 0

1,225,000

1,225,000

Inspection Fees

75,000

75,000

Equipment/Furnishing

0

Total Cost:

510,000 350,000

860,000

0 1,300,000

0

0

0

2,160,000

FUNDING SCHEDULE

R8750 Paygo R3140 Federal TAP R7000 Future Bonds R7100 Prior Bonds

150,000

150,000 580,000 70,000 60,000

150,000

300,000 280,000

1,040,000

1,620,000

70,000

260,000

330,000 60,000

60,000

0

0

Total Cost:

510,000 350,000

860,000

0 1,300,000

0

0

0

2,160,000