FY 23 APPROVED CAPITAL BUDGET
Trappe Church Road Bridge #161
HIGHWAYS - BRIDGES Project Number:
Operating Budget Impact
H224503
Council District:
E
Revenues:
Location:
Darlington
Expenditures: Cost Savings: None:
Est. Debt Service:
$3,500
(annual)
X
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status: FY 22-23: Design FY 24: Right of way and permits FY 26: Construction
PROJECT DESCRIPTION: The purpose of this project is to replace the superstructure for the bridge that carries Trappe Church Road over Hollands Branch due to deteriorated beams. The project is eligible for Federal funding. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
500,000 200,000
700,000
700,000 50,000
0 0 0 0
50,000
Construction
1,200,000
1,200,000
Inspection Fees
100,000
100,000
Equipment/Furnishing
0
Total Cost:
500,000 200,000
700,000
50,000
0 1,300,000
0
0
2,050,000
FUNDING SCHEDULE
R3140 Federal TAP R7000 Future Bonds R7100 Prior Bonds
400,000 160,000
560,000 40,000 100,000
1,040,000
1,600,000
40,000
50,000
260,000
350,000 100,000
100,000
0 0
0 0
Total Cost:
500,000 200,000
700,000
50,000
0 1,300,000
0
0
2,050,000