FY 23 APPROVED CAPITAL BUDGET
US 40 Water Main Replacement
WATER Project Number: Council District:
Operating Budget Impact
W196149 Multiple Aberdeen
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$15,000 (annual)
X
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status: Spring 2022: Study/design scope development 2023-2024: Construction anticipated to begin
PROJECT DESCRIPTION: This project will allow for the design and construction of a parallel or replacement water main along route 40 to replace the existing aged pipe.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
600,000
600,000 250,000
250,000
1,100,000
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
Total Cost:
600,000
0
600,000 250,000
0 250,000
0
0
1,100,000
FUNDING SCHEDULE
R7100 Prior Bonds R7000 Future Bonds
600,000
600,000
600,000 500,000
0 250,000
250,000
0 0 0
0 0 0
Total Cost:
600,000
0
600,000 250,000
0 250,000
0
0
1,100,000