FY 23 APPROVED CAPITAL BUDGET
Renewal and Replacement Sewer Infrastructure
SEWER Project Number: Council District:
Operating Budget Impact
S126726 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 2/9/22: $1,100,853
Project Schedule/Status: Reline or replace sewer line section downstream of ps manholes at McPhail Road - 2021-2022; Bel Forest cleanout replacement/lining 2022; Aerial pipeline coatings 2023-2024; Harford Square sewer 2025. This project is ongoing and used as required when advanced deterioration of piping system is discovered through field investigations.
PROJECT DESCRIPTION: This project will provide funding for modeling, design and construction to refurbish or replace major sewer mains, manholes, vaults, pumping stations, and apparatus that have reached or are nearing the end of their useful life. This project also funds emergency projects for sewer system upgrades from breaks or failures.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
0 500,000
900,000 200,000
1,600,000
0
0
Construction
2,150,000 100,000 2,250,000 300,000 1,500,000
4,050,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
2,150,000 100,000 2,250,000 800,000 1,500,000 900,000 200,000
0
5,650,000
FUNDING SCHEDULE
R8750 Paygo R7000 Future Bonds
2,150,000 100,000 2,250,000 800,000
200,000
3,250,000 2,400,000
0 0 0 0
1,500,000 900,000
0 0 0
Total Cost:
2,150,000 100,000 2,250,000 800,000 1,500,000 900,000 200,000
0
5,650,000