FY 23 APPROVED CAPITAL BUDGET
Lower Bynum Run Interceptor Phase 6&7
SEWER Project Number: Council District:
Operating Budget Impact
S096703
C
Revenues:
Location:
Emmorton
Expenditures: Cost Savings: None:
Est. Debt Service:
$216,179 (annual)
X
Expended/Encumbered as of 2/9/22: $7,618,845
Project Schedule/Status: Phase 7 is complete, the design for phase 6 of the project is modeling dependent, estimated for calendar year 2021.
PROJECT DESCRIPTION: This project will provide for the funding of design, permits and construction of a parallel to the existing Bynum Run interceptor, from Wheel Road to the Plumtree Interceptor, near MacPhail. This project consists of two phases. Phase 6 is approximately 5,200 linear feet from GIS Asset ID manhole #104091 and traverse from Wheel Road to Patterson Mill Road. Phase 7 is approximately 6,400 linear feet from GIS Asset ID manhole #104091 to manhole #104200 and runs from near Patterson Mill Road to MacPhail Road. This project is required to ensure capacity for new connections in the Development Envelope surrounding Bel Air and to help avoid sanitary sewer overflows.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
1,370,000
1,370,000
1,370,000
0
0
Construction
7,750,324
7,750,324
7,750,324
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
9,120,324
0 9,120,324
0
0
0
0
0
9,120,324
FUNDING SCHEDULE
R7100 Prior Bonds R8750 Paygo
8,647,154
8,647,154
8,647,154
473,170
473,170
473,170
0 0 0
0 0 0
Total Cost:
9,120,324
0 9,120,324
0
0
0
0
0
9,120,324