Project Schedule/Status:
PROJECT DESCRIPTION: This project will provide funding to expand the Harford Metro Area Network (HMAN) backbone and lateral dark fiber to unserved areas of the County. This expansion will allow an Internet Service Provider to build infrastructure from the backbone and laterals and to provide internet service to these unserved areas. Appropriation authority is provided in this budget to accept Federal and State grant funding through grants such as the American Rescue Plan Act (ARPA), the Statewide Broadband Infrastructure grant programs, and other various grant mechanisms for broadband expansion to unserved regions. For FY 23 Federal authority has been reallocated from the Highways Infrastructure Capital Project @ $10,000,000; the HCSO Fleet Replacement Project a@ $6,000,000 and State appropriation authority from the HMAN Capital project in the amount of $6,000,000.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
25,000,000 25,000,000
25,000,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
0 25,000,000 25,000,000
0
0
0
0
0 25,000,000
FUNDING SCHEDULE
R3161 ARPA R3399 State Other R3199 Federal Other
10,000,000 10,000,000 9,000,000 9,000,000 6,000,000 6,000,000
10,000,000 9,000,000 6,000,000
0 0 0
0 0 0
Total Cost:
0 25,000,000 25,000,000
0
0
0
0
0 25,000,000