FY 23 APPROVED CAPITAL BUDGET
Facilities Repair Program
GENERAL Project Number: Council District:
Operating Budget Impact
A234105 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$125,000 (annual)
X
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status: FY 23: Northern Precinct, HCSO DC HVAC inmate housing, Circuit Court fire alarm, Circuit Court ceremonial courtrool electrical upgrade, Hdg Activity Ctr roof replacement, Whiteford Library parking lot replacement.
PROJECT DESCRIPTION: This project provides funding for the replacement, renovation, and repairs of county building systems (site, roofing, structural, exterior, interior, mechanical, plumbing, electrical, fire/life safety, and conveyances).
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
410,000
410,000 200,000 200,000 200,000 200,000 200,000
1,410,000
0
0
Construction
4,590,000 4,590,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 13,590,000
Inspection Fees
0 0
0
Equipment/Furnishing
0 0 5,000,000 5,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 15,000,000
Total Cost:
FUNDING SCHEDULE
R7000 Future Bonds
5,000,000 5,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 15,000,000 0 0 0 0 0 0 0 0 0 5,000,000 5,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 15,000,000