FY 23 APPROVED CAPITAL BUDGET
Riverside Area Watershed Restoration
WATERSHED MANAGEMENT Project Number: M234110 Council District: F Location: Riverside Est. Debt Service:
Operating Budget Impact
Revenues:
Expenditures: Cost Savings: None:
$30,000 (annual)
0
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status:
PROJECT DESCRIPTION: The Declaration Run and adjacent Riverside watersheds are located in Riverside. The headwaters of Declaration Run begin at the intersection of MD Rt. 7 and MD Rt. 543 and discharge near the confluence of Bynum Run with Bush River. The Riverside watershed discharges directly to Bush Creek and includes the Riverside community. This project will fund the restoration projects prioritized through the watershed assessments (2014) that are the most cost effective project to improve water quality. Water quality projects are required under the county's municipal NPDES or MS4 permit and through the Chesapeake Bay Watershed Implementation Plan as required under the Bay TMDL.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
620,000
620,000
70,000 150,000
70,000 150,000
70,000
1,130,000
0
0
Construction
1,000,000 1,000,000 300,000 682,000 300,000 682,000 300,000
3,264,000
Inspection Fees
80,000
80,000
30,000
68,000
30,000
68,000
30,000
306,000
Equipment/Furnishing
0
0
Total Cost:
0 1,700,000 1,700,000 400,000 900,000 400,000 900,000 400,000
4,700,000
FUNDING SCHEDULE R7000 Future Bonds R3320 State DNR/SWM
1,200,000 1,200,000 400,000 400,000 400,000 400,000 400,000
3,200,000 1,500,000
500,000
500,000
500,000
500,000
0 0 0
0 0 0
Total Cost:
0 1,700,000 1,700,000 400,000 900,000 400,000 900,000 400,000