FY 24 APPROVED CAPITAL BUDGET BOOK
Rush Road Bridge #97
HIGHWAYS - BRIDGES Project Number:
Operating Budget Impact
H244502
Council District:
D
Revenues:
Location:
Jarrettsville
Expenditures: Cost Savings: None:
Est. Debt Service:
$8,400
(annual)
X
Expended/Encumbered as of 1/9/23: $0
Project Schedule/Status: FY 24: Design FY 25: Right of way and permits FY 26: Construction
PROJECT DESCRIPTION: This project will replace the existing bridge on Rush Road over Kellogg Branch. The current structure is a single lane bridge and is posted at 24,000 lbs for single unit vehicles and 43,000 lbs for combination vehicles. The new bridge would eliminate posting and provide a two lane bridge. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
400,000
400,000
400,000 25,000 900,000 100,000
0 0 0 0
25,000
Construction
900,000 100,000
Inspection Fees
Equipment/Furnishing
0
Total Cost:
0 400,000
400,000
25,000 1,000,000
0
0
0
1,425,000
FUNDING SCHEDULE
R7000 Future Bonds
400,000
400,000
25,000 1,000,000
1,425,000
0 0 0 0
0 0 0 0
Total Cost:
0 400,000
400,000
25,000 1,000,000
0
0
0
1,425,000