FY 24 APPROVED CAPITAL BUDGET BOOK
Plum Tree Collector Sewer and Pumping Station
SEWER Project Number: Council District:
Operating Budget Impact
New
A
Revenues:
Location:
Bel Air
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 1/9/23: $0
Project Schedule/Status: Design and construction in outyears.
PROJECT DESCRIPTION: This project is for the upgrade and capacity increase to the Plum Tree Pumping Station and Collector Sewer. The project is needed to provide adequate capacity to growth in the Fallston Sanitary Subdistrict Capacity Study.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
0 0 0 0 0 0 0 0 0 0 0 0
250,000
250,000
2,500,000 3,100,000 8,000,000 13,600,000
Construction
0 0 0
Inspection Fees
Equipment/Furnishing
Total Cost:
0
0
0 250,000 2,500,000 3,100,000 8,000,000 13,850,000
FUNDING SCHEDULE
R8750 Paygo R7000 Future Bonds
250,000
250,000
2,500,000 3,100,000 8,000,000 13,600,000
0 0 0
Total Cost:
0
0
0 250,000 2,500,000 3,100,000 8,000,000 13,850,000
435