FY 24 APPROVED CAPITAL BUDGET BOOK
Magnolia Sewer Petition
SEWER Project Number: Council District:
Operating Budget Impact
S205428
B
Revenues:
Location:
Edgewood
Expenditures: Cost Savings: None:
Est. Debt Service:
$1,785
(annual)
X
Expended/Encumbered as of 1/9/23: $51,291
Project Schedule/Status: Preliminary design is complete. Design in 2021-2022 and construction anticipated for 2023.
PROJECT DESCRIPTION: This project involves the planning, land acquisition, design and construction of a gravity sewer to service the Magnolia sewer petition area. This petition project is located along Magnolia Road, just south of the intersection of Magnolia Road and Hanson Road. There is $72,000 expected in grant funding from the Stormwater Management Septic System Disconnection Program.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
85,000
85,000
85,000
0
0
Construction
604,500
604,500
604,500
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
689,500
0
689,500
0
0
0
0
0
689,500
FUNDING SCHEDULE
R7100 Prior Bonds R3399 State Other R7910 State Loan
85,000 72,000 532,500
85,000 72,000 532,500
85,000 72,000 532,500
0 0
0 0
Total Cost:
689,500
0
689,500
0
0
0
0
0
689,500
438