FY 24 APPROVED CAPITAL BUDGET BOOK
Woodbridge Sewer Petition
SEWER Project Number: Council District:
Operating Budget Impact
S205429
B
Revenues:
Location:
Fallston $8,085
Expenditures: Cost Savings: None:
Est. Debt Service:
(annual)
X
Expended/Encumbered as of1/9/23: $0
Project Schedule/Status: Design phase underway; construction to begin calendar year 2023.
PROJECT DESCRIPTION: This project involves the planning, land acquisition, design and construction of both gravity sewer and a small diameter grinder pump system to service the Woodridge sewer petition area. This petition project is located south of Bel Air Road, north of Whitaker Mill Road, and east of Joppa Road.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
385,000
385,000
385,000
0
0
Construction
3,635,300
3,635,300
3,635,300
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
4,020,300
0 4,020,300
0
0
0
0
0
4,020,300
FUNDING SCHEDULE
R7100 Prior Bonds R3399 State Other R7910 State Loan
385,000 355,500
385,000 355,500
385,000 355,500
3,279,800
3,279,800
3,279,800
0 0
0 0
Total Cost:
4,020,300
0 4,020,300
0
0
0
0
0
4,020,300