FY 25 Harford County Approved Capital Budget
Public Safety Complex
PUBLIC SAFETY Project Number: Council District:
Operating Budget Impact
E244107
E
Revenues:
Location:
Bel Air
Expenditures: Cost Savings: None:
X
Est. Debt Service:
$120,000 (annual)
Expended/Encumbered as of 2/22/24: $0
Project Schedule/Status:
PROJECT DESCRIPTION: This project is for the design and construction associated with a Public Safety Complex. Construction will occur in multiple phases to include Fire, EMS, and Law Enforcement.
Estimated total construction cost is $45,000,000.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029
FY 2030
TOTAL
Engineering/Design Land Acquisition
1,000,000
1,000,000
1,000,000
0
0
Construction
4,000,000
4,000,000
11,250,000 11,250,000 26,500,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
5,000,000
0 5,000,000
0
0
0 11,250,000 11,250,000 27,500,000
FUNDING SCHEDULE
R7100 Prior Bonds R7000 Future Bonds
5,000,000
5,000,000
5,000,000
0 0 0 0
11,250,000 11,250,000 22,500,000
0 0 0
Total Cost:
5,000,000
0 5,000,000
0
0
0 11,250,000 11,250,000 27,500,000