FY 25 Harford County Approved Capital Budget
Bakerfield Elementary School
BOARD OF EDUCATION Project Number:
Operating Budget Impact
B234121
Council District:
F
Revenues:
Location:
Havre de Grace
Expenditures: Cost Savings: None:
Est. Debt Service:
$4,457
(annual)
X
Expended/Encumbered as of 1/9/23: $7,200
Project Schedule/Status: This project will be closed and removed from the Capital Improvement Program following completion of the audit.
PROJECT DESCRIPTION: The funds will be used to replace the 23 year old failing air-cooled water chiller with a new energy efficient air-cooled chiller. Recently, it has experienced increased failures that caused the school to be without cooling for a short period. Future problems could lead to additional damage done to the internal components of the chiller. There is a risk of possible permanent damage and loss of cooling for an extended period of time.
Amendment - requested by HCPS to reallocate funds to FY 25 capital budget. Prior bonds will be reallocated to the following capital project: HCPS Facilities Master Plan (B214116): 412,773
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
151,000
151,000
151,000
0
0
Construction
1,109,000 (412,773)
696,227
696,227
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
1,260,000 (412,773)
847,227
0
0
0
0
0
847,227
FUNDING SCHEDULE
R7920 State Bonds R7100 Prior Bonds
635,000
635,000 212,227
635,000 212,227
625,000 (412,773)
0 0 0
0 0 0
Total Cost:
1,260,000 (412,773)
847,227
0
0
0
0
0
847,227
148