FY 25 Harford County Approved Capital Budget
Homestead Wakefield Elementary Major Project
BOARD OF EDUCATION Project Number:
Operating Budget Impact
B224106
Council District:
C
Revenues:
Location:
Bel Air
Expenditures: Cost Savings: None:
Est. Debt Service:
$1,231,200 (annual)
X
Expended/Encumbered as of 2/22/24: $801,584
Project Schedule/Status: Pending Litigation Design complete. Project ready to bid and begin construction.
PROJECT DESCRIPTION: Homestead Wakefield Elementary School in Bel Air, MD consists of three (3) separate structures. The entire campus consists of approximately 115,458 square feet. The Wakefield school building was constructed in 1958 and consists of approximately 58,425 square feet. In 1966, the Homestead building was constructed, which consist of approximately 52,628 square feet. A remote kindergarten building was constructed near the Wakefield building in 1968 and consists of approximately 4,585 square feet. The three building school is aged, antiquated, inefficient and poses many safety concerns. Additionally, forty feet of elevation separates Wakefield from Homestead adding to the complexity of operating a three building campus. The site also has stormwater issues, traffic congestion without a separate bus drop off loop, aged playground equipment, and a 50 year underground storage tank. The building equipment is at its end of life, there are building leaks, lighting issues, major HVAC concerns, and lack of ADA compliance. The program space for educational purposed are inadequate. A revised scope study recommending completely\ replacing the Homestead/Wakefield Elementary school on the site of the Wakefield building was approved by the BOE in February 2021. The scope study also analyzed the facility capacity in coordination with the balancing enrollment study. It was determined that a capacity of 1,100 students was needed to address capacity concerns in the area. Education specifications have been developed and approved by the local BOE and MSDE. The project is currently in design and construction to begin in 2021. This request is for the first year of construction funding. This project will be the number 1 priority for the State portion. EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
6,000,000
6,000,000
6,000,000
0
0
Construction
58,343,000 23,125,000 81,468,000
81,468,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
64,343,000 23,125,000 87,468,000
0
0
0
0
0 87,468,000
FUNDING SCHEDULE
R7920 State Bonds R7000 Future Bonds R7100 Prior Bonds R8750 Paygo
36,168,000
36,168,000
36,168,000 23,125,000 28,175,000
23,125,000 23,125,000
28,175,000
28,175,000
0 0
0 0
Total Cost:
64,343,000 23,125,000 87,468,000
0
0
0
0
0 87,468,000
156