FY 25 Harford County Approved Capital Budget
ADA Improvements
PARKS AND RECREATION Project Number:
Operating Budget Impact
P144120 Multiple Various
Council District:
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 2/22/24: $310,323
Project Schedule/Status: Engineering and construction
PROJECT DESCRIPTION: This project reflects Harford County's commitment to provide access to County parks for individuals with disabilities. All new and recently reconstructed facilities meet these standards. This project will provide funding for the necessary engineering and construction to improve older facilities. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
470,000 230,000
700,000 140,000 140,000 140,000 140,000 150,000
1,410,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
470,000 230,000
700,000 140,000 140,000 140,000 140,000 150,000
1,410,000
FUNDING SCHEDULE R1515 Recordation Tax R6999 Other
350,000 205,000
555,000 140,000 140,000 140,000 140,000 150,000
1,265,000
120,000
25,000
145,000
145,000
0 0 0
0 0 0
Total Cost:
470,000 230,000
700,000 140,000 140,000 140,000 140,000 150,000
1,410,000