FY 25 Harford County Approved Capital Budget
Gunpowder River Dredging 12
PARKS AND RECREATION Project Number:
Operating Budget Impact
P124121
Council District:
A
Revenues:
Location:
Joppatowne
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 2/22/24: $1,791,801
Project Schedule/Status: This project will be closed and remaining funds will be reallocated to the new Gunpowder River Dredging Capital Project.
PROJECT DESCRIPTION: This project proposes maintenance dredging of the existing navigation channel in Taylor's Creek, as well as the channel leading into Gunpowder River which provides boating access to the Joppatowne community.
This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.
FY 25 - funds will be reallocated to the New Gunpowder River Dredging Capital Project.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
550,000
550,000
550,000
0
0
Construction
1,550,000 (122,174)
1,427,826
1,427,826
Inspection Fees
134,000
134,000
134,000
Equipment/Furnishing
0
0
Total Cost:
2,234,000 (122,174)
2,111,826
0
0
0
0
0
2,111,826
FUNDING SCHEDULE R3399 State Other R1515 Recordation Tax
1,720,000
1,720,000
1,720,000
514,000 (122,174)
391,826
391,826
0 0 0
0 0 0
Total Cost:
2,234,000 (122,174)
2,111,826
0
0
0
0
0
2,111,826
200