FY 25 Harford County Approved Capital Budget
Chestnut Hill Road Bridge #41
HIGHWAYS - BRIDGES Project Number:
Operating Budget Impact
New
Council District:
D
Revenues:
Location:
Forest Hill
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 2/22/24: $0
Project Schedule/Status: FY 27/28: Design FY 29: Right-of-Way
PROJECT DESCRIPTION: This project will replace the existing bridge on Chestnut Hill Road over Cabbage Branch. The current structure is a single lane bridge and is posted at 25,000 lbs for a single unit vehicle and 46,000 lbs for combination vehicles. The new bridge would eliminate posting and provide a new two lane bridge. The project is necessary due to the deterioration of the bridge deck and steel beams, and is eligible for Federal funding. The project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0 0 0 0 0 0 0 0 0 0 0
300,000 300,000
600,000 25,000
25,000
Construction
0 0 0
Inspection Fees
Equipment/Furnishing
Total Cost:
0
0
0 300,000 300,000
25,000
0
625,000
FUNDING SCHEDULE
R3140 Federal TAP R7000 Future Bonds
240,000 240,000
480,000 145,000
60,000
60,000
25,000
0 0 0
Total Cost:
0
0
0 300,000 300,000
25,000
0
625,000