FY 25 Harford County Approved Capital Budget

Old Pylesville Road Bridge #138

HIGHWAYS - BRIDGES Project Number:

Operating Budget Impact

New

Council District:

D

Revenues:

Location:

Pylesville

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 2/22/24: $0

Project Schedule/Status: FY 30: Design

PROJECT DESCRIPTION: This project will replace the existing bridge on Old Pylesville Road over Jacks Hole stream. The current structure is a poor rated structure with both the deck and supestructure in poor condition. Replacement of the bridge will remove a poor rated bridge from the County inventory.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

0 0 0 0 0 0 0 0 0 0 0 0

400,000

400,000

0 0 0 0

Construction

Inspection Fees

Equipment/Furnishing

Total Cost:

0

0

0

0

0

0 400,000

400,000

FUNDING SCHEDULE

R7000 Future Bonds

400,000

400,000

0 0 0 0

Total Cost:

0

0

0

0

0

0 400,000

400,000

320