FY 25 Harford County Approved Capital Budget

Traffic Calming, Bicycle & Road Safety Improvements

HIGHWAYS - ROADS Project Number:

Operating Budget Impact

H104513 Multiple Various

Council District:

Revenues:

Location:

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 2/22/24: $952,936

Project Schedule/Status: Various projects are continuously being designed and constructed under this account.

PROJECT DESCRIPTION: To reduce vehicular speeds in communities, this project will construct various "traffic calming" devices aimed at speed reduction, community beautification, and increased safety. The project will be directed at communities with fairly high traffic volumes, 85th percentile speeds greater than 10 MPH over the speed limit, small average lot sizes, and a high percentage of cut-through traffic. With recent interest in Complete Streets and road safety in general for all users, funds are also being provided for bicycle and automobile related safety improvements.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

110,000

15,000

125,000

10,000

10,000

10,000

10,000

10,000

175,000

0

0

Construction

845,000 127,500

972,500 102,500

85,000

85,000

85,000

85,000

85,000

1,397,500

Inspection Fees

95,000

7,500

5,000

5,000

5,000

5,000

5,000

127,500

Equipment/Furnishing

0

0

Total Cost:

1,050,000 150,000 1,200,000 100,000 100,000 100,000 100,000 100,000

1,700,000

FUNDING SCHEDULE

R8750 Paygo

1,050,000 150,000 1,200,000 100,000 100,000 100,000 100,000 100,000

1,700,000

0 0 0 0

0 0 0 0

Total Cost:

1,050,000 150,000 1,200,000 100,000 100,000 100,000 100,000 100,000

1,700,000

345