FY 25 Harford County Approved Capital Budget
Major Renovations/Construction County Facilities
GENERAL Project Number: Council District:
Operating Budget Impact
A244103 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$137,346 (annual)
X
Expended/Encumbered as of 2/22/24: $615,892
Project Schedule/Status:
Engineering/design fees associated with feasibility & program studies and concept plans. Includes roof repalcements or major building upgrades.
PROJECT DESCRIPTION: This project will provide funding for major renovations/construction of County owned Facilities. DPW Capital Projects will oversee and manage this project.
Amended per council amendment #33
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
250,000 500,000
750,000
750,000
0
0
Construction
3,750,000 1,222,737 4,972,737 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 11,972,737
Inspection Fees
0 0
0
Equipment/Furnishing
0 4,000,000 1,722,737 5,722,737 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 12,722,737
Total Cost:
FUNDING SCHEDULE
R7000 Future Bonds R7100 Prior Bonds
1,722,737 1,722,737 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000
8,722,737 4,000,000
4,000,000
4,000,000
0 0 0
0 0
0 4,000,000 1,722,737 5,722,737 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 12,722,737
Total Cost: