FY 25 Harford County Proposed Capital Budget & Capital Improvement Program
HCPL Technology
LIBRARIES Project Number: Council District:
Operating Budget Impact
L124118 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
N/A
(annual)
X
Expended/Encumbered as of 2/22/24: $1,962,411
Project Schedule/Status:
PROJECT DESCRIPTION: This project provides for replacing public and staff computers for the branches and the administrative office, primarily on a four year cycle.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
2,509,100 200,000 2,709,100 200,000 200,000 200,000 200,000 200,000 2,509,100 200,000 2,709,100 200,000 200,000 200,000 200,000 200,000
3,709,100 3,709,100
Total Cost:
FUNDING SCHEDULE
R8750 Paygo
2,509,100 200,000 2,709,100 200,000 200,000 200,000 200,000 200,000
3,709,100
0 0 0 0
0 0 0 0
Total Cost:
2,509,100 200,000 2,709,100 200,000 200,000 200,000 200,000 200,000
3,709,100
130