HWDC Landfill Capping 10

SOLID WASTE Project Number: Council District:

Operating Budget Impact

D105601

D

Revenues:

Location:

Street

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 2/22/24: $7,977,097

Project Schedule/Status:

PROJECT DESCRIPTION: This project provides for the planning, design, and construction of the capping system required by the Refuse Disposal Permit for proper closure and post-closure of completed landfill cells at the Harford Waste Disposal Center (HWDC) including related studies, activities, equipment and appurtenances. This project relates to the Harford County ten year Solid Waste Management Plan.

This project will be closed and the remaining balance will be reappropriated to a new Landfill Capping Project.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

400,000

400,000

400,000

0

0

Construction

9,270,000 (1,842,904)

7,427,096

7,427,096

Inspection Fees

150,000

150,000

150,000

Equipment/Furnishing

0

0

Total Cost:

9,820,000 (1,842,904)

7,977,096

0

0

0

0

0

7,977,096

FUNDING SCHEDULE

R8750 Paygo R8751 Prior Paygo

9,820,000

9,820,000 (1,842,904)

9,820,000 (1,842,904)

(1,842,904)

0 0 0

0 0 0

Total Cost:

9,820,000 (1,842,904)

7,977,096

0

0

0

0

0

7,977,096