FY 25 Harford County Proposed Capital Budget & Capital Improvement Program
Cedar Lane Park Improvements
Project Number: Council District:
Operating Budget Impact Revenues:
P244113
C
Location:
Bel Air, MD
Expenditures: Cost Savings: None:
Est. Debt Service:
N/A
(annual)
Expended/Encumbered as of 2/22/24: $0
Project Schedule/Status:
PROJECT DESCRIPTION: This project provides appropriation authority for the improvements and amenities at the regional field sports park. This project supports the goals and objectives of the 2022 Land Preservation, Parks, and Recreation Plan and its Capital Improvement Program Recommendations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
1,500,000 1,500,000
1,500,000
Inspection Fees
0
0
Equipment/Furnishing
3,000,000
3,000,000
3,000,000 4,500,000
Total Cost:
3,000,000 1,500,000 4,500,000
0
0
0
0
0
FUNDING SCHEDULE
R6999 Other
3,000,000 1,500,000 4,500,000
4,500,000
0 0 0 0
0 0 0 0
Total Cost:
3,000,000 1,500,000 4,500,000
0
0
0
0
0
4,500,000
176