FY 25 Harford County Proposed Capital Budget & Capital Improvement Program

Edgeley Grove Farm

PARKS AND RECREATION Project Number:

Operating Budget Impact

P184113

Council District:

B

Revenues:

Location:

Benson

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 2/22/24: $67,209

Project Schedule/Status:

PROJECT DESCRIPTION: This project proposes the construction and renovation of recreation facilities in Edgeley Grove Farm. Future development of active recreation facilities including additional parking will occur as funding is available. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

5,000 150,000

155,000

155,000

0

0

Construction

130,000

130,000

750,000

880,000

Inspection Fees

5,000

5,000

5,000

Equipment/Furnishing

0

0

Total Cost:

140,000 150,000

290,000

0 750,000

0

0

0

1,040,000

FUNDING SCHEDULE R1515 Recordation Tax R3380 Prog. Open Sp.

140,000 150,000

290,000

500,000 250,000

790,000 250,000

0 0 0 0

0 0 0

Total Cost:

140,000 150,000

290,000

0 750,000

0

0

0

1,040,000