FY 25 PROPOSED CAPITAL IMPROVEMENT PROGRAM

Total

Prior Approp Budget Year 2025

FY 2026

FY 2027

FY 2028

FY 2029

FY 2030

PUBLIC SAFETY

FY 25 Projects Ambulance/Other Emergency Fleet HCDC Facility Repairs/Upgrades HCSO Body Worn Camera Program HCSO Fleet Replacement HCSO In-Car Camera Systems HCSO Mobile Data Term Replace Mobile/Portable Radio System Upgrade Public Safety Comm in School Bldgs

10,000,000 10,140,000 4,197,600 12,530,000 3,136,350 2,301,900 30,000,000 1,150,000 5,825,000 11,000,000 9,260,000 22,700,000 27,235,000 5,000,000 27,500,000 2,500,000 1,000,000 37,494,525 600,000 8,465,000 1,800,000 4,700,000 3,000,000 4,725,000 1,200,000 59,193,875 2,662,318 81,500,000 67,316,500 27,598,000 7,402,000 1,787,682 247,460,375

1,000,000 3,640,000 1,795,000 6,000,000 935,000 1,086,400 850,000 4,725,000 7,000,000 6,210,000 1,200,000 15,235,000 0 1,000,000 37,494,525 600,000 8,465,000 1,800,000 4,700,000 3,000,000 4,725,000 1,200,000 26,794,425 2,662,318 64,316,500 15,598,000 7,402,000 0 117,660,925 0 5,000,000 0

1,500,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000

3,000,000 1,000,000 1,000,000

500,000

500,000

500,000

801,000

800,800

800,800

0

0

0

1,530,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000

550,000 203,000

550,450 202,500

550,450 202,500 100,000 100,000

550,450 202,500

0

0

202,500

202,500

5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000

100,000 600,000 4,000,000 550,000

0

0

100,000 100,000

0

Public Safety Equipment Riverside Fire & EMS Station

100,000

100,000

100,000

0

0

0

0

0

VFC Facility Repair

500,000

500,000

500,000

500,000

500,000

Whiteford VFC - New Station 911 Emergency Communications

1,000,000 7,000,000 7,000,000 6,500,000

0

0

2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000

Outyear Projects CAD Replacement Public Safety Complex Open Projects Darlington VFC House #1

0 5,000,000

0 0

0

0

0

0 0 0 0 0 0 0 0 0 0 0

0

0 11,250,000 11,250,000

Special Ops Equipment Replacement

500,000

500,000

500,000

500,000

500,000

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

Emergency Ops Center Complex (old) HCSO Crisis Neg/Cell Site Sim Rep Mobile/Portable Radio System Upgrade 18 Multi-Agency Pub Safety Mobile Command Ctr

North Harford Station

SHCO House 1 Replacement VFC Public Safety Equipment

Whiteford VFC Reno of Main Station

PUBLIC SAFETY BY PROJECT

20,834,000 25,153,750 20,253,750 18,352,950 22,652,500 22,552,500

Paygo

4,934,000 10,153,750 5,253,750 4,352,950 3,902,500 3,802,500

Reappropriated Future Bonds

0

0

0

0

0

0

10,000,000 13,000,000 13,000,000 12,000,000 16,750,000 16,750,000

Prior Bonds

3,000,000

0

0

0

0

0

State

2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000

Federal

0

0 0

0 0

0 0

0 0

0 0

Other

887,682

900,000

PUBLIC SAFETY BY FUND

247,460,375

117,660,925

20,834,000 25,153,750 20,253,750 18,352,950 22,652,500 22,552,500

HARFORD COMMUNITY COLLEGE

FY 25 Projects Chesapeake Welcome Center Open Projects Fallston Hall Renovations

57,632,794

46,119,794

11,513,000

0

0

0

0

0

7,232,375

7,232,375

0

0

0

0

0

0

HCC BY PROJECT

64,865,169

53,352,169

11,513,000

0

0

0

0

0

HARFORD COMMUNITY COLLEGE

325,000

Future Bonds Prior Bonds

0

325,000

0 0 0 0

0 0 0 0

0 0 0 0

0 0 0 0

0 0 0 0

32,704,000 29,903,169 1,933,000

32,704,000 20,648,169

0

State Other

9,255,000 1,933,000

0

HCC BY FUND

64,865,169

53,352,169

11,513,000

0

0

0

0

0

28