FY 25 Harford County Proposed Capital Budget & Capital Improvement Program
Fleet Replacement
WATER & SEWER MISCELLANEOUS Project Number: O126727 Council District: Multiple Location: Various Est. Debt Service: $0
Operating Budget Impact
Revenues:
Expenditures: Cost Savings: None:
(annual)
X
Expended/Encumbered as of 2/22/24: $9,216,078
Project Schedule/Status: This project will be managed/controlled by the Department of Procurement, Fleet Management Division.
PROJECT DESCRIPTION: This project will provide funds for the replacement of essential vehicles and equipment to enable using agencies to perform their critical jobs. Funds will allow the county to maintain a consistent rotation, which lowers maintenance costs, fuel efficiency, and fleet availability. Units to be replaced are on average 10 years old which have high mileage and are unreliable.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
9,772,000 500,000 10,272,000 500,000 500,000 500,000 500,000 500,000 12,772,000 9,772,000 500,000 10,272,000 500,000 500,000 500,000 500,000 500,000 12,772,000
Total Cost:
FUNDING SCHEDULE
R8750 Paygo
9,772,000 500,000 10,272,000 500,000 500,000 500,000 500,000 500,000 12,772,000 0 0 0 0 0 0 0 0 9,772,000 500,000 10,272,000 500,000 500,000 500,000 500,000 500,000 12,772,000
Total Cost:
417