FY 25 Harford County Proposed Capital Budget & Capital Improvement Program
Water & Sewer Billing Project
WATER & SEWER MISCELLANEOUS Project Number: O156007 Council District: Multiple Location: Various Est. Debt Service: $0
Operating Budget Impact Revenues:
Expenditures: Cost Savings:
(annual)
None: X
Expended/Encumbered as of 2/22/24: $1,221,801
Project Schedule/Status: Implementation is complete for the new billing system project. FY24 - Billing rate evaluation
PROJECT DESCRIPTION: This capital project is to procure and implement a replacement Water and Sewer Utility Billing System. The current billing system is over 30 years old and is based on previous legacy software. Because of this expense, maintenance efforts and potential risk of business interruption associated with this technology, a replacement application is required. A new replacement system will have enhancements to improve the business process of collecting revenue and improving service to over 43,600 water and sewer customers. A new billing rate evaluation is also planned for FY24-25. Includes integrations with upgraded meter reading equipment and software.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
2,500,000
2,500,000
2,500,000
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
Total Cost:
2,500,000
0 2,500,000
0
0
0
0
0
2,500,000
FUNDING SCHEDULE
2,500,000
2,500,000
2,500,000
R8750 Paygo
0 0 0 0
0 0 0 0
Total Cost:
2,500,000
0 2,500,000
0
0
0
0
0
2,500,000