Major Renovations/Construction County Facilities
GENERAL Project Number: Council District:
Operating Budget Impact
A244103 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$180,000 (annual)
X
Expended/Encumbered as of 2/22/24: $615,892
Project Schedule/Status:
Engineering/design fees associated with feasibility & program studies and concept plans. Includes roof repalcements or major building upgrades.
PROJECT DESCRIPTION: This project will provide funding for major renovations/construction of County owned Facilities. DPW Capital Projects will oversee and manage this project.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
250,000 500,000
750,000
750,000
0
0
Construction
3,750,000 3,000,000 6,750,000 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 13,750,000
Inspection Fees
0 0
0
Equipment/Furnishing
0 4,000,000 3,500,000 7,500,000 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 14,500,000
Total Cost:
FUNDING SCHEDULE
R7000 Future Bonds R7100 Prior Bonds
3,500,000 3,500,000 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 10,500,000
4,000,000
4,000,000
4,000,000
0 0 0
0 0
0 4,000,000 3,500,000 7,500,000 2,000,000 2,000,000 1,000,000 1,000,000 1,000,000 14,500,000