CAPITAL PROJECTS THAT IMPACT THE OPERATING BUDGET
Impacts of capital projects on the operating budget are considered as part of the County's capital planning process. These impacts can be positive or negative and include things such as maintenance, utilities, personnel, equipment, debt service, or cost savings. Future expenses associated with the operation and/or maintenace of capital assets are estimated and included in capital and operating budgets. Capital projects included in the budget that have prior and current county bond funding incur signfiicant debt service. The County must take necessary steps to assure repayment. Bonds are typically used to finance the capital portion of tax supported general public purpose governmental activities, including schools, public safety, highways, and water and sewer uses. The Capital Impact on Operating section of bond funded project sheets lists an estimated annual debt service cost.
Estimated Operating Impact
Total 6 year Project Cost (Including Prior)
FY 26 Budget Appropriation
Operating Budget Impact
Project Title
FY 26
FY 27
FY 28
FY 29
FY 30
FY 31
TOTAL
GENERAL PROJECTS: Bank Building Renovation Broadband Infrastructure Efficiency Capital Investment Facility Repair/Life Cycle
$3,500,000 $3,500,000 Debt Service $1,500,000 $45,320,000 Maintenance $2,500,000 $19,700,460 Debt Service $1,000,000 $38,480,000 Maintenance $205,000
$100,450
$95,428 $2,500 ($30,900)
$90,405 $3,000 ($31,827)
$85,383 $3,500 ($32,782)
$80,360 $4,000 ($33,765)
$75,338 $4,500 ($34,778)
$527,364 $19,500 ($194,052) $1,431,482 $2,700,000 $3,751,809 $1,427,305 $5,493,632 $1,521,819 $3,239,514 $1,699,200 $904,050 $210,000 $2,450,000 $1,000,482 $5,162,304 $1,506,750 $2,555,022 $1,205,400 $753,375 $3,901,088
$2,000
$2,515,400 Energy Efficiency ($30,000)
$272,663 $400,000 $714,630 $271,868 $289,870 $617,050 $283,200 $172,200 $21,209 $10,000 $350,000 $190,568 $860,384 $287,000 $395,000 $229,600 $143,500 $600,000 $15,000 $10,000 $315,700 $937,385 $238,641
$259,030 $245,397 $420,000 $440,000 $678,899 $643,167 $258,274 $244,681 $275,377 $260,883 $586,198 $555,345 $283,200 $283,200 $163,590 $154,980
$231,764 $218,131 $204,497 $460,000 $480,000 $500,000 $607,436 $571,704 $535,973 $231,087 $217,494 $203,901 $866,212 $815,258 $764,305 $246,390 $231,896 $217,403 $524,493 $493,640 $462,788 $283,200 $283,200 $283,200 $146,370 $137,760 $129,150
HMAN General
Debt Service
Major Reno County Facilities $3,750,000 $9,472,737 Debt Service
Site Acquisition
$5,000,000 $48,104,161 Debt Service
$1,162,573 $968,119 $917,165
Courthouse Building Repairs $0
$10,334,900 Debt Service $22,500,000 Debt Service $7,050,000 Debt Service $1,344,000 Debt Service Utilities/Maint
HCSO Central Precinct
$0
Humane Society
$0 $0
Under/Aboveground Tanks
$20,149 $111,348 $4,277,713 $3,979,864 $3,825,484 $3,671,081 $3,516,645 $3,362,184 $22,632,971 $19,088 $18,028 $16,967 $15,907
PUBLIC SAFETY: DES Fleet Replacement EMS Safety Equipment HCSO Fleet Replacement Mobile/Portable Radio 25
$1,500,000 $11,500,000 Maint./Fuel
$20,000
$30,000
$40,000
$50,000
$60,000
$300,000
$2,300,000 Maint. Contract
$380,000 $400,000 $181,040 $171,511 $860,384 $860,384 $272,650 $258,300 $406,850 $419,056 $218,120 $206,640 $136,325 $129,150 $618,000 $636,540
$420,000 $440,000 $460,000 $161,983 $152,454 $142,926 $860,384 $860,384 $860,384 $243,950 $229,600 $215,250 $431,627 $444,576 $457,913 $195,160 $183,680 $172,200 $121,975 $114,800 $107,625 $657,546 $681,217 $707,785
HCDC Facility Repairs/Upgrade $3,000,000 $10,890,000 Debt Service
$1,250,000 $15,780,000 Equipment $5,000,000 $35,000,000 Debt Service
Maintenance
$1,780,000 $1,833,400 $1,888,402 $1,945,054 $2,003,406 $2,063,508 $11,513,770
911 Emergency Communication $2,000,000 $29,235,000 Maintenance Whiteford VFC - New Station $7,000,000 $22,700,000 Debt Service
Public Safety Complex
$0
$45,000,000 Debt Service $11,000,000 Personnel
Belcamp Fire and EMS Station $0
Utilities
$15,405 $10,270
$15,867 $10,578
$16,391 $10,927
$16,981 $11,321
$17,643 $11,762
$97,287 $64,858
Maintenance Debt Service
$299,915 $284,130 $890,516 $843,647 $226,708 $214,776
$268,345 $252,560 $236,775 $796,777 $749,908 $703,039 $202,844 $190,912 $178,980
$1,657,425 $4,921,272
Emergency Operations Complex $0
$37,494,525 Debt Service $8,465,000 Debt Service
Mobile Portable Radio 18
$0
$1,252,861 $6,362,778 $6,369,583 $6,368,981 $6,372,963 $6,381,799 $6,395,790 $38,251,894
HARFORD COMMUNITY COLLEGE: Regional Workforce Dev. Center $9,000,000 $47,000,000 Debt Service
$229,600 $848,499 $99,433
$218,120 $206,640 $806,074 $763,649
$195,160 $183,680 $172,200 $721,224 $678,799 $636,374
$1,205,400 $4,454,619 $522,025 $6,182,044
Chesapeake Welcome Center $0
$57,632,794 Debt Service $7,232,375 Debt Service
Fallston Hall Renovations
$0
$94,462
$89,490
$84,518
$79,547
$74,575
$1,177,532 $1,118,656 $1,059,779 $1,000,902 $942,026 $883,149
HARFORD COUNTY PUBLIC LIBRARIES: Bel Air Library Renovations $0
$6,382,000 Debt Service
$39,463
$37,489
$35,516
$33,543
$31,570
$29,597
$207,178
HARFORD COUNTY PUBLIC SCHOOLS: Blueprint Facility Program $2,002,500 $8,952,500 Debt Service C. Milton Wright HS Limited Reno$7,000,000 $86,101,400 Debt Service
$91,912 $200,900 $212,224 $35,875 $982,114 $317,313 $106,334 $111,167 $409,764 $40,299 $11,427 $6,478 $34,440 $39,357 $23,271 $9,680 $6,091 $464
$87,316
$82,721
$78,125
$73,529
$68,934
$482,537 $1,054,725 $1,114,177 $6,328,350 $188,344 $5,156,099 $1,665,893 $558,251 $583,627 $2,151,259 $50,820 $31,977 $2,435 $211,569 $59,952
$190,855 $180,810 $201,613 $191,002
$170,765 $160,720 $150,675 $180,391 $169,779 $159,168
Educational Facility Program $500,000
$13,590,247 Debt Service
Harford Academy Major Proj.
$26,000,000 $156,000,000 Debt Service
$1,205,400 $1,145,130 $1,084,860 $1,024,590 $964,320 $904,050
HCPS Facilities Master Plan $750,000
$4,180,000 Debt Service
$34,081
$32,288
$30,494
$28,700
$26,906
Harford Technical HS Reno $16,000,000 $74,606,000 Debt Service Life, Health, Safety/Compliance $5,000,000 $19,264,311 Debt Service
$933,008 $883,903 $301,447 $285,582 $101,017 $95,700 $105,609 $100,050 $389,275 $368,787
$834,797 $785,691 $736,586 $269,716 $253,850 $237,985
Roof Replacement NHHS
$8,336,880 $8,336,880 Debt Service
$90,383 $94,492
$85,067 $88,934
$79,750 $83,375
Major HVAC
$0 $0
$19,838,879 Debt Service $34,174,475 Debt Service $1,833,507 Debt Service $15,210,159 Debt Service $6,073,665 Debt Service $6,053,156 Debt Service $87,468,000 Debt Service $3,244,000 Debt Service $3,700,314 Debt Service $2,055,851 Debt Service $847,227 Debt Service $665,730 Debt Service
Aberdeen MS HVAC Reno
$348,299 $327,811 $307,323
Athletic & Rec Repairs/Improve $0 Bakerfield Elementary School $0
$9,196 $5,786
$8,712 $5,482
$8,228 $5,177
$7,744 $4,873
$7,260 $4,568
Fleet Replacement
$0
$441
$417
$394
$371
$348
HCPS Facility Repair Program $0
$38,284 $10,853 $6,155 $32,718 $37,389 $22,108
$36,269 $10,279 $5,831 $30,996 $35,421 $20,944
$34,254 $9,705 $5,507 $29,274 $33,453 $19,781
$32,239 $9,131 $5,183 $34,010 $31,485 $18,617
$30,224 $8,557 $4,859 $25,830 $29,518 $17,454
HCPS Site Improvements Homestead Wakefield ES
$0 $0 $0 $0
$1,472,310 $1,398,695 $1,325,079 $1,251,464 $1,177,848 $1,104,233 $7,729,629
Meadowvale Elementary School $0
$34,013 $187,268 $206,623 $122,175
NHHS Recovery Units Prospect Mill ES Roof
Roof Replace. Bakerfield ES $0