FY 26 Harford County Proposed Capital Budget Book
Hookers Mill Road Bridge #13
HIGHWAYS - BRIDGES Project Number:
Expended/Encumbered as of 2/4/25: $173,422
H224501
Council District:
F
Location:
Abingdon
Project Schedule/Status: FY 22-27: Design FY 27: Right of Way/ Permits/ Utility FY 28: Construction
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project is to replace the entire bridge that carries Hookers Mill Road over Bynum Run. The beams, deck and abutments are deteriorated and should be replaced in the next several years. This project is eligible for Federal funding. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2026 Approp Total
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
Engineering/Design Land Acquisition
1,050,000
1,050,000
1,050,000
50,000
50,000
50,000
Construction
0 1,250,000 1,250,000
2,500,000
Inspection Fees
0 0
75,000
75,000
150,000
Equipment/Furnishing
0
Total Cost:
1,100,000
0 1,100,000 1,325,000 1,325,000
0
0
0 3,750,000
FUNDING SCHEDULE
R3140 Federal TAP R7100 Prior Bonds R7000 Future Bonds
840,000 260,000
840,000 1,060,000 1,060,000
2,960,000
260,000
260,000 530,000
265,000 265,000
Total Cost:
1,100,000
0 1,100,000 1,325,000 1,325,000
0
0
0 3,750,000
Estimated Debt Service ESTIMATED OPERATING BUDGET IMPACT:
FY 2026
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL 39,176
7,462
7,089
6,716
6,343
5,970
5,597
297
Made with FlippingBook Ebook Creator