FY 26 Proposed Capital Budget Book
VFC Facility Repair
PUBLIC SAFETY Project Number: Council District:
Expended/Encumbered as of 2/4/25: $6,129,544
E154104 Multiple Various
Location:
Project Schedule/Status:
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides funds for the facility repair/renovation costs for existing stations to be determined/approved by the Harford County Volunteer Fire and EMS Association for systemic repairs, roofs, paving, HVAC and other minor renovations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2026 Approp Total
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
6,760,000 500,000 7,260,000 500,000 500,000 500,000 500,000 500,000
9,760,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
6,760,000 500,000 7,260,000 500,000 500,000 500,000 500,000 500,000
9,760,000
FUNDING SCHEDULE
R3161 ARPA R8750 Paygo
1,400,000
1,400,000
1,400,000 8,360,000
5,360,000 500,000 5,860,000 500,000 500,000 500,000 500,000 500,000
0 0 0
0 0 0
Total Cost:
6,760,000 500,000 7,260,000 500,000 500,000 500,000 500,000 500,000
9,760,000
ESTIMATED OPERATING BUDGET IMPACT:
FY 2026
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
102
Made with FlippingBook flipbook maker