FY 26 Proposed Capital Budget Book
HCPS Facilities Master Plan
BOARD OF EDUCATION Project Number:
Expended/Encumbered as of 2/4/25: $847,656
B214116 Multiple Various
Council District:
Location:
Project Schedule/Status:
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project allows Harford County Public Schools (HCPS) to plan for facility needs, program needs, balance enrollment, and develop scope studies for major capital projects. HCPS believes proper planning is imperative to efficiently maintaining facilities to provide a safe, secure, and healthy learning environment that is conducive to effective teaching and learning, creativity and innovation. FY 26 funding for consulting services dedicated to redistricting efforts. This initiative is planned to align with the opening of the new elementary school, the Harford Academy project. It aims to proactively address enrollment shifts, support the implementation of the Blueprint for Maryland's Future, and enhance resource allocation to meet evolving educational needs.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2026 Approp Total
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
Engineering/Design Land Acquisition
1,570,000 750,000 2,320,000 300,000 600,000 315,000 320,000 325,000
4,180,000
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
Total Cost:
1,570,000 750,000 2,320,000 300,000 600,000 315,000 320,000 325,000
4,180,000
FUNDING SCHEDULE
R8750 Paygo R7100 Prior Bonds R7000 Future Bonds
1,070,000
1,070,000
1,070,000
500,000
500,000
500,000
750,000
750,000 300,000 600,000 315,000 320,000 325,000
2,610,000
0 0
0 0
Total Cost:
1,570,000 750,000 2,320,000 300,000 600,000 315,000 320,000 325,000
4,180,000
ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service
FY 2026 35,875
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
188,344
34,081
32,288
30,494
28,700
26,906