FY 26 Proposed Capital Budget Book

HCPS Site Improvements

BOARD OF EDUCATION Project Number:

Expended/Encumbered as of 2/4/25 $915,930

B224105 Multiple Various

Council District:

Location:

Project Schedule/Status:

Expended/Enc.

Budget

PROJECT DESCRIPTION: This project is used to maintain and complete improvements to HCPS sites including stormwater management facilities, septic facilities, paving overlay and new paving. These projects keep HCPS sites compliant with local, state and federal laws and regulations.

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031

TOTAL

Cost Element

Prior

FY 2026 Approp Total

Engineering/Design Land Acquisition

0 0

0 0

Construction

6,053,156

6,053,156

6,053,156

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

6,053,156

0 6,053,156

0

0

0

0

0

6,053,156

FUNDING SCHEDULE

R8750 Paygo R6999 Other BOE R7100 Prior Bonds R1525 Transfer Tax

500,000

500,000

500,000

3,775,000

3,775,000

3,775,000

398,156

398,156

398,156

1,380,000

1,380,000

1,380,000

0

0

Total Cost:

6,053,156

0 6,053,156

0

0

0

0

0

6,053,156

ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service

FY 2026 11,427

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031

TOTAL 59,952

10,853

10,279

9,705

9,131

8,557

152