FY 26 Proposed Capital Budget Book
Technology Infrastructure
BOARD OF EDUCATION Project Number:
Expended/Encumbered as of 2/4/25: $4,347,249
B214111 Various Multiple
Council District:
Location:
Project Schedule/Status:
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project addresses critical investments required for a rapidly growing, technology rich environment. These investments are essential to maintain a high level of operational efficiency, avoid obsolescence, and preserve compatibility to industry standards for technology infrastructure components. This over-arching project includes refresh programs to network infrastructure, information security, data storage, communications equipment, servers and auditorium/gymnasium audio/video/theatrical lighting systems.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2026 Approp Total
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
Engineering/Design Land Acquisition
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
17,280,502 17,280,502
17,280,502
17,280,502
Total Cost:
0 17,280,502
0
0
0
0
0 17,280,502
FUNDING SCHEDULE
R8750 Paygo R1525 Transfer Tax R6999 Other BOE
6,614,986
6,614,986
6,614,986
10,874
10,874
10,874
10,654,642
10,654,642
10,654,642
0
0
Total Cost:
17,280,502
0 17,280,502
0
0
0
0
0 17,280,502
ESTIMATED OPERATING BUDGET IMPACT:
FY 2026
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
162