FY 26 Proposed Capital Budget Book

Prospect Mill Park

PARKS AND RECREATION Project Number:

Expended/Encumbered as of 2/4/25: $167,661

P224116

Council District:

E

Location:

Fountain Green

Project Schedule/Status:

Expended/Enc.

Budget

PROJECT DESCRIPTION: Harford County developed a 29.9 acre parcel to serve the outdoor recreation needs of the Hickory/Fountain Green area. Amenities such as a storage building, picnic pavilion, and playground will be constructed. Additional residential development is anticipated in this community. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program recommendations.

EXPENDITURE SCHEDULE

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031

TOTAL

Cost Element

Prior

FY 2026 Approp Total

Engineering/Design Land Acquisition

0 0

0 0

Construction

250,000 250,000

500,000 200,000

600,000

1,300,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

250,000 250,000

500,000 200,000

0

0 600,000

0

1,300,000

FUNDING SCHEDULE R1515 Recordation Tax R3380 Program Open Space

250,000 100,000

350,000 100,000 150,000 100,000

300,000 300,000

750,000 550,000

150,000

0 0 0

0 0 0

Total Cost:

250,000 250,000

500,000 200,000

0

0 600,000

0

1,300,000

ESTIMATED OPERATING BUDGET IMPACT:

FY 2026

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031

TOTAL

194