FY 26 Proposed Capital Budget Book

Bynum Run Watershed Restoration Improvements

WATERSHED MANAGEMENT Project Number: M234108 Council District: Multiple Location: Various Project Schedule/Status:

Expended/Encumbered as of 2/4/25: $3,516,934

Expended/Enc.

Budget

PROJECT DESCRIPTION: The Bynum Run Watershed (15,000 acres) begins in Forest Hill near the intersection of Jarrettsville Road and MD Route 24 and drains into the Bush River near Rt. 543 and Rt. 40. Assessments of the watershed were completed (Upper Bynum 2017) and (Middle-Lower Bynum 2019) and prioritized recommendations for restoration projects, including stream restorations and stormwater management retrofits that provide the most cost effective improvements to water quality. Water quality restoration projects are required under the County's municipal NPDES or MS4 permit and through the Chesapeake Bay Watershed Implementation Plan as required under the Bay TMDL.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2026 Approp Total

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031

TOTAL

Engineering/Design Land Acquisition

1,400,000 200,000 1,600,000 200,000 100,000

0

0

0

1,900,000

0

0

Construction

4,865,000 700,000 5,565,000 700,000 350,000

0 0

0 0

0 0

6,615,000

Inspection Fees

585,000 100,000

685,000 100,000

50,000

835,000

Equipment/Furnishing

0

0

Total Cost:

6,850,000 1,000,000 7,850,000 1,000,000 500,000

0

0

0

9,350,000

FUNDING SCHEDULE R7100 Prior Bonds R3320 State DNR/SWM R7000 Future Bonds

5,102,125 1,500,000

5,102,125 1,500,000

5,102,125 1,500,000 2,500,000

1,000,000 1,000,000 1,000,000 500,000

0

0

0

R8750 Paygo

247,875

247,875

247,875

0

0

Total Cost:

6,850,000 1,000,000 7,850,000 1,000,000 500,000

0

0

0

9,350,000

ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service

FY 2026 175,131

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 166,374 157,618 148,861 140,105 131,348

TOTAL

919,438