FY 26 Proposed Capital Budget Book

Bridge Deck Replacements

HIGHWAYS - BRIDGES Project Number:

Expended/Encumbered as of 2/4/25: $0

New

Council District:

Multiple Various

Location:

Project Schedule/Status: FY 29: Design FY 31: Construction

Expended/Enc.

Budget

PROJECT DESCRIPTION: This project is for the design and replacement of deteriorated corrugated metal bridge decks throughout the County. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future needs of the County.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2026 Approp Total

FY 2027 FY 2028 FY 2029 FY 2030

FY 2031

TOTAL

Engineering/Design Land Acquisition

0 0 0 0 0 0 0 0 0 0 0 0

400,000

400,000

0

Construction

900,000 900,000 100,000 100,000

Inspection Fees

Equipment/Furnishing

0

Total Cost:

0

0

0

0 400,000

0 1,000,000 1,400,000

FUNDING SCHEDULE

0

0

0 400,000

0 1,000,000 1,400,000

R8750 Paygo

0 0 0 0

Total Cost:

0

0

0

0 400,000

0 1,000,000 1,400,000

ESTIMATED OPERATING BUDGET IMPACT:

FY 2026

FY 2027 FY 2028 FY 2029 FY 2030

FY 2031

TOTAL

289