FY 26 Proposed Capital Budget Book
Havre de Grace Water Treatment Plant Upgrade
WATER Project Number: Council District:
Expended/Encumbered as of 2/4/25: $558,855
W196141
F
Location:
Havre de Grace
Project Schedule/Status: FY24 - Complete baffle & piping designs FY25 - Baffle & piping construction FY26 - Control room and lab upgrades FY28 - Solids handling upgrades
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project shall allow for the study, design and construction of plant improvements required throughout the plant due to technology and regulatory requirements, in addition to aging equipment. Project work includes: clearwell baffle wall replacement; filter-to-waste piping improvement; control room & lab upgrades; chemical feed system upgrades; solids handling upgrades.
EXPENDITURE SCHEDULE
FY 2027 FY 2028 FY 2029 FY 2030
FY 2031
TOTAL
Cost Element
Prior
FY 2026 Approp Total
Engineering/Design Land Acquisition
150,000
150,000
200,000
350,000
0
0
Construction
1,000,000
1,000,000
500,000
1,500,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
1,150,000
0 1,150,000
0 200,000 500,000
0
0
1,850,000
FUNDING SCHEDULE
R7000 Future Bonds R7100 Prior Bonds R8750 Paygo
1,150,000
1,150,000
1,150,000
0 0 0 0
200,000
200,000 500,000
500,000
0 0
Total Cost:
1,150,000
0 1,150,000
0 200,000 500,000
0
0
1,850,000
FY 2026 33,005
FY 2027 FY 2028 FY 2029 FY 2030
FY 2031 24,754
TOTAL
ESTIMATED OPERATING BUDGET IMPACT:
173,276
Estimated Debt Service
31,355
29,705
28,054
26,404