FY 26 Proposed Capital Budget Book
Infiltration and Inflow
SEWER Project Number: Council District:
Expended/Encumbered as of 2/4/25: $873,414
S106714 Multiple Various
Location:
Project Schedule/Status: FY25 - Comprehensive Sewer System study FY25 - Sewer and manhole inspection and rehabilitation
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project is to identify and locate major sources of infiltration and inflow in the County's sewer collection system and execute projects for rehabilitation. Projects shall consist of studies, designs, sewer system modeling, modeling software upgrades and modeling technical support, smoke testing, flow metering, inspections, and televising sewer lines and manholes as well as executing small rehabilitation projects for cleaning, grouting, slip lining, lining, coating or other sewer line or manhole repair. This project will also include a countywide sewer comprehensive study to identify deficiencies in the collection system. Project work includes: sewer and manhole inspections; sewer and manhole rehabilitation and repair; comprehensive sewer system study and 5 year updates; miscellaneous sewer modeling; sewer flow monitoring.
EXPENDITURE SCHEDULE
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
Cost Element
Prior
FY 2026 Approp Total
Engineering/Design Land Acquisition
1,900,000 100,000 2,000,000 100,000 100,000 100,000 450,000
2,750,000
0
0
Construction
500,000 200,000
700,000 200,000 200,000 200,000 200,000 200,000
1,700,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
2,400,000 300,000 2,700,000 300,000 300,000 300,000 650,000 200,000
4,450,000
FUNDING SCHEDULE
2,400,000 300,000 2,700,000 300,000 300,000 300,000 650,000 200,000
4,450,000
R8750 Paygo
0 0 0 0
0 0 0 0
Total Cost:
2,400,000 300,000 2,700,000 300,000 300,000 300,000 650,000 200,000
4,450,000
ESTIMATED OPERATING BUDGET IMPACT:
FY 2026
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
377