Public Safety Complex
PUBLIC SAFETY Project Number: Council District:
Expended/Encumbered as of 2/3/26: $127,680
E244107
E
Location:
Bel Air
Project Schedule/Status:
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project is for the design and construction of a post-frame building to house the Special Operations divison, and ambulances that respond from the 2220 Ady Road Emergency Services complex.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031
FY 2032
TOTAL
Engineering/Design Land Acquisition
1,000,000
1,000,000
1,000,000
0
0
Construction
4,000,000 1,500,000 5,500,000
5,500,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
5,000,000 1,500,000 6,500,000
0
0
0
0
0
6,500,000
FUNDING SCHEDULE
R7100 Prior Bonds R7000 Future Bonds
5,000,000
5,000,000
5,000,000 1,500,000
1,500,000 1,500,000
0 0 0
0 0 0
Total Cost:
5,000,000 1,500,000 6,500,000
0
0
0
0
0
6,500,000
ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service
FY 2027 167,000
FY 2028 FY 2029 FY 2030 FY 2031
FY 2032
TOTAL
876,750
158,650 150,300 141,950 133,600 125,250
102