FY 27 Proposed Capital Budget
HCPS Facility Repair Program
BOARD OF EDUCATION Project Number:
Expended/Encumbered as of 2/3/26: $496,265
B204131 Multiple Various
Council District:
Location:
Project Schedule/Status:
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides for the repair, renovation, and replacement of school flooring, bleachers, lockers, folding partitions, building envelope, roofing repairs, and other building components and equipment as needed.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
6,073,665
6,073,665
6,073,665
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
6,073,665
0 6,073,665
0
0
0
0
0
6,073,665
FUNDING SCHEDULE
R7100 Prior Bonds R8750 Paygo R6999 Other BOE
1,404,148
1,404,148
1,404,148
19,517
19,517
19,517
4,650,000
4,650,000
4,650,000
0 0
0 0
Total Cost:
6,073,665
0 6,073,665
0
0
0
0
0
6,073,665
ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service
FY 2027 46,899
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
241,268
44,554
42,209
39,864
37,519
30,224
149
Made with FlippingBook Ebook Creator