FY 27 Proposed Capital Budget
Solid Waste Facilities Repair Program
SOLID WASTE Project Number: Council District:
Expended/Encumbered as of 2/3/26: $1,300,828
D204115
D
Location:
Street
Project Schedule/Status: This project is ongoing.
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides funding for the replacement, renovation and repairs of DPW-Solid Waste Facilities, to include site improvements, facility upgrades, roofing, structural, electrical, mechanical, equipment, appurtenances, property acquistion, and investigation, engineering, and permitting. This project relates to the Harford County ten year Solid Waste Management Plan.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
2,500,000
2,500,000 1,000,000 6,000,000 4,000,000 2,000,000 500,000 16,000,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
2,500,000
0 2,500,000 1,000,000 6,000,000 4,000,000 2,000,000 500,000 16,000,000
FUNDING SCHEDULE
R7100 Prior Bonds R8750 Paygo R7000 Future Bonds
2,000,000
2,000,000
2,000,000
500,000
500,000 1,000,000 6,000,000 4,000,000 2,000,000 500,000 14,000,000 0 0 0 0 0 0 0 2,500,000 1,000,000 6,000,000 4,000,000 2,000,000 500,000 16,000,000
Total Cost:
2,500,000
ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service
FY 2027 66,800
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
350,700
63,460
60,120
56,780
53,440
50,100
170