FY 27 Proposed Capital Budget

Eden Mill Park Rehabilitation

PARKS AND RECREATION Project Number:

Expended/Encumbered as of 2/3/26: $1,071,287

P104113

Council District:

D

Location:

Pylesville

Project Schedule/Status:

Expended/Enc.

Budget

PROJECT DESCRIPTION: This project continues renovations and improvements to Eden Mill, including renovations to the dam and canoe/kayak launch. Maintenance and upgrading of the existing facilities is critical to protecting the County's investment in this historic building and increased usability as a nature center and community attraction. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation plan and its Capital Improvement Program recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2027 Approp Total

FY 2028 FY 2029 FY 2030 FY 2031 FY 2032

TOTAL

Engineering/Design Land Acquisition

50,000

50,000

50,000

0

0

Construction

1,605,000 125,000 1,730,000 500,000

2,230,000

Inspection Fees

50,000

50,000

50,000

Equipment/Furnishing

0

0

Total Cost:

1,705,000 125,000 1,830,000 500,000

0

0

0

0

2,330,000

FUNDING SCHEDULE R6999 Other R1515 Recordation Tax R3380 Program Open Space

300,000

300,000

300,000

1,205,000 125,000 1,330,000 500,000

1,830,000

200,000

200,000

200,000

0 0

0 0

Total Cost:

1,705,000 125,000 1,830,000 500,000

0

0

0

0

2,330,000

ESTIMATED OPERATING BUDGET IMPACT:

FY 2027

FY 2028 FY 2029 FY 2030 FY 2031 FY 2032

TOTAL

185

Made with FlippingBook Ebook Creator