FY 27 Proposed Capital Budget
Heavenly Waters Park - Soma
PARKS AND RECREATION Project Number:
Expended/Encumbered as of 2/3/26: $0
P254116
Council District:
B
Location:
Benson
Project Schedule/Status:
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project proposes the development of a passive park on the Soma area of Heavenly Waters Park. The County is working to complete the repurchase of 25 acres on the site. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
200,000
200,000 100,000
300,000
0
0
Construction
450,210
450,210 250,000
700,210
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
650,210
0
650,210 350,000
0
0
0
0
1,000,210
FUNDING SCHEDULE R1515 Recordation Tax R3380 Prog. Open Space R8750 Paygo
300,000 350,000
300,000 150,000 350,000 200,000
450,000 550,000
210
210
210
0
0
Total Cost:
650,210
0
650,210 350,000
0
0
0
0
1,000,210
ESTIMATED OPERATING BUDGET IMPACT:
FY 2027
FY 2028 FY 2028=9 FY 2030 FY 2031 FY 2032
TOTAL
215
Made with FlippingBook Ebook Creator